[PIN] Renewal of platform C Hannover HBF
TenderZenith matches this tender's eligibility criteria against your company profile to calculate a deterministic qualification score and identify potential disqualifiers.
A structured breakdown of scope, eligibility requirements, submission steps, and key conditions — extracted directly from the official notice.
Sign in to unlock Bid Fit & AI Opportunity Intelligence
TenderZenith calculates a personalized qualification score against your company profile and extracts structured intelligence from tender documents with your 7-Day Pro Trial (No Credit Card Required).
Description & Project Overview
Several routes have their origins in Hanover Central Station. In platform C, tracks 7 and 8 belong to route 1710 in the western area and to route 1733 in the eastern area. The construction work for the renewal of platform C is taking place on DB AG land.
The property owner is DB-Fahrwege. Information on general measures
- Construction of the project is scheduled to begin in spring 2029.
- In 2029, the temporary construction will be built to maintain the track in operation.
- The platform roof will then be dismantled and the platform including the underlying sealing structures will be replaced.
- In 2030, the platform roof above the platform as well as all sealing structures in the track area will be replaced.
- The planned end of construction is at the end of 2030.
The construction is divided into the following construction phases: Construction phase 0: new construction of electrical shafts, construction of temporary enclosure Construction phase 1: construction of temporary construction (steel frame, stair portals, post ramp) Construction phase 2: construction of temporary roof covering enclosure, dismantling of roof covering and technical. Equipment on the roof Construction phase 3: Assembly of the roof covering, prov. ramp roofing, dismantling of the platform roof of track 7 Construction phase 4: Dismantling of the platform roof of track 8 Construction phase 5: Dismantling and new construction of the platform of track 7 Construction phase 6: Dismantling and new construction of the platform of track 8 Construction phase 7: New construction of the platform roof of track 8 Construction phase 8: New construction of platform roof on track 7, installation of roof equipment, dismantling of temporary structures Construction phase 9-10: Construction of waiting shelters, renewal of the renovation structures in the track area Eq. 40+7 Construction phase 11: Renewal of the renovation structures in the track area Eq. 70+8