Pre-Solicitation Notice - Trenching, Conduit and Ground-well Installation
TenderZenith matches this tender's eligibility criteria against your company profile to calculate a deterministic qualification score and identify potential disqualifiers.
A structured breakdown of scope, eligibility requirements, submission steps, and key conditions — extracted directly from the official notice.
Sign in to unlock Bid Fit & AI Opportunity Intelligence
TenderZenith calculates a personalized qualification score against your company profile and extracts structured intelligence from tender documents with your 7-Day Pro Trial (No Credit Card Required).
Description & Project Overview
Pre-Solicitation Notice - Trenching, Conduit and Ground-well Installation
Description
the united stated embassy in kingston, jamaica, plans to issue a request for quotations (rfq) for trenching, conduit and ground-well installation in various locations on the embassy compound.
scope of work: the contractor will provide all labor, equipment, supervision, material specific to the back filling and compaction and management needed to complete the job
infrastructure support system - handhole / underground conduit system
trenching
nine locations have been identified requiring trench work.
thirteen locations have been identified requiring trench work.
before excavation, the contractor shall locate and verify all existing utilities in the proposed trench alignment.
if excavation interferes with existing drains, piping, or structures, the contractor shall immediately notify, in writing, the cor and provide temporary protection for these systems before proceeding.
trenching from handholes
the contractor shall make wall penetrations into existing manholes/handholes as required for the number and size of conduits entering and exiting each structure, in accordance with the drawings.
conduit
existing conduit shall remain in place unless the drawings specifically direct removal or modification.
under grass, soil, the contractor shall install schedule 80 pvc conduit with a minimum cover of 24 inches (610 mm) from finished grade to top of conduit, or as indicated on the drawings, whichever is greater.
all underground 90 degree bends with a 12inch (305 mm) radius shall use prefabricated sweeping bends.
above grade, all underground pvc conduit shall transition to rigid galvanized steel (rgs) using pvc to rgs couplers.
the contractor shall install pull lines in all new conduit runs.
soil and backfill materials
soil materials
the contractor shall provide all labor and materials for soil and backfill, where required.
select backfill: astm d 2487 soil classification groups sw, sp, and sm, or combinations thereof; free of rock or gravel larger than 3 inches (75 mm), debris, waste, frozen materials, vegetation, and other deleterious matter.
asphalt/concrete base course: naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; astm d 2940; with at least 95% passing a 11/2inch (40 mm) sieve and not more than 8% passing a 1/4inch (6.4 mm) sieve.
base gravel: naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; astm d 2940; 100% passing a 1inch (25 mm) sieve and not more than 8% passing a 1/4inch (6.4 mm) sieve.
sand cushion: astm c 33 fine aggregate, natural or manufactured sand.
placement and compaction
place backfill and fill in layers not exceeding:
8 inches (203 mm) loose thickness for heavy compaction equipment;
4 inches (102 mm) loose thickness when compacted by hand-operated tampers.
place backfill and fill evenly to the required elevations, uniformly along their full length.
compact soil materials to not less than the following percentages of maximum dry unit weight per astm d 1557:
under lawns or unpaved areas: scarify and re-compact top 6 inches (152 mm) below subgrade and compact each layer to 85%.
utility trenches: compact each layer of initial and final backfill to 85%.
anticipated period of performance: a base period of twenty-one (21) days after contract award
eligibility and registration
offerors must hold an active registration in the system for award management (sam.gov) when they submit a proposal and at award.
local insurance and defense based act (dba) insurance.
solicitation availability
the embassy will post the solicitation and all amendments only on sam.gov at https://sam.gov. interested parties should monitor sam.gov for the release and any amendments. the embassy will not issue paper copies.
disclaimer
this notice is for informational purposes only and is not a request for proposals. it does not commit the government to issue a solicitation or award a contract. the government will not pay for any information or materials submitted in response to this notice.
interested parties are required to send their interest to kingstonquotes@state.gov on or before october 26, 2026 at 2pm local time.
Related Procurement Opportunities
Similar tenders in Construction materials, Infrastructure and construction, Engineering